Medical Center Drive will be repaved in upcoming weeks, with the work scheduled to take place over the course of four weekends.
- Nov. 13-15: Phase 1 work starts at Pierce Avenue to the ambulance parking on the East side. This phase will start Friday, Nov. 13 after 6 p.m. and will conclude Sunday, Nov. 15 at 5 p.m.
- Nov. 20-22: Phase 2 work starts at Pierce Avenue to the ambulance parking on the West side. This phase will start Friday, Nov. 20 at 6 p.m. and conclude Sunday, Nov. 22 at 5 p.m.
- Nov. 27-29: Phase 3 work starts at ambulance parking to 21st Avenue South on the East side. This phase will start Friday, Nov. 27 at 6 p.m. and conclude Sunday, Nov. 29 at 5 p.m.
- Dec. 4-6: Phase 4 work starts at the ambulance parking to 21st Avenue South on the West side. This phase will start Friday, Dec. 4 at 6 p.m. and conclude Sunday, Dec. 6 at 5 p.m.
In addition to the repaving, updated striping will be added to the street, and a new crosswalk, to be between the Emergency Department walk-in entrance and Vanderbilt University Hospital, will be added.
The last time Medical Center Drive was repaved was in 2009.